Even as Chennai Metro Rail is racing ahead to meet the October
deadline of the first commercial run from Koyambedu to Alandur, it is
highly unlikely that the seven stations in the stretch would be ready
before October end.
While officials are maintaining the October deadline, but metro rail
workers confide that the deadline is likely to be stretched further.
“It could be here and there or may be stretched further but we expect
it to be over by the end of the year,” a metro rail source said.
The biggest issue bothering the metro rail officials is the pending
work on all the seven metro rail stations. While work is progressing
at a faster pace, it is unlikely that the work would be completed
before October end.
While work in CMBT is nearing completion with minor electrical as well
as commissioning and testing of lifts and escalators is in progress,
some interior work like flooring, plastering, painting and false
ceiling is still pending.
In Vadapalani, the structural work is still in progress. Work has yet
to start on erecting lift and escalators. In Ekkatuthangal, the work
on erecting lift as well as escalators is in progress. Interestingly,
the structural works in all other stations except Vadapalani has been
completed.
Work was hit in the stations due to delayed work by Consolidated
Construction Consortium, whose contract was terminated. A new
contract was drafted and work was awarded to four firms --
Tiruchitambalam Projects Limited (TPL), Saraswati Construction
Company, Nagarjuna Construction Company and URC Constructions.
Factfile on stations:
Koyambedu
Contractor: Tiruchitambalam Projects Limited
Works completed: Structural work, indoor and outdoor installation of
signals , telecommunications, roof truss erection
In progress: Flooring, plastering, painting and false ceiling;
electrical works; testing and commissioning of lifts and escalators
Yet to Start: roof sheeting work
CMBT:
Contractor: Tiruchitambalam Projects Limited
Works completed: Structural works; erection of lift and escalator
completed; indoor and outdoor installation of signals;
telecommunication equipment installation; roofworks
In progress: Interior works like flooring, plastering, painting and
false ceiling, testing and commissioning of lifts and escalators;
electrical works.
Arumbakkam
Contractor: Tiruchitambalam Projects Limited
Works completed: Structural works; roof works; Indoor and outdoor
installation of signals
In progress: Interior works like flooring, plastering and false
ceiling; testing and commissioning of lifts and escalators; electrical
works; telecommunication works
Vadapalani
Contractor: URC Constructions
Works completed: Roof truss erection
In progress: Structural works; electrical works; Telecommunication
works; indoor signalling
Works yet to be started: Lifts and escalators; Roof sheeting work;
outdoor signalling
Ashok Nagar
Contractor: Saraswathi Construction Company
Works completed: Structural works; installation of indoor and outdoor signals
In progress: Interior works like flooring, plastering and painting;
Testing and commissioning of lifts and escalators; telecommunication
works
Yet to be started: roof sheeting work
Ekkatuthangal
Contractor: Nagarjuna Construction Company
Works Completed: Structural works
In progress: Interior works like flooring, plastering, painting and
wall tile; erection of lifts and escalators; Roof fabrication works
Yet to start: Indoor and outdoor signaling and telecommunication works
Alandur
Contractor: Nagarjuna Construction Company
Works completed: Structural works; indoor signalling
In progress: Interior works like flooring, plastering, painting and
wall tile; erection of lifts and escalators; roof works;
telecommunication works
Yet to start: Outdoor installation of signals yet to start