CMDA's proposed bus terminus lacks entry and exit points
C Shivakumar
C Shivakumar
Chennai:
The work on the much-awaited satellite bus terminus in
Madhavaram, which will cater to commuters going to neighbouring Andhra Pradesh,
has started but it looks like the planning body’s project is facing issues over
how it is going to have entry and exit points at the proposed terminus.
The bus terminal project is to be built at a cost of Rs
94.16 crore after CMDA approved the tender by BNR Infrastructure Projects at a
hurriedly convened authority meeting just prior to the announcement of assembly
elections.
But now it emerges that the project, which is coming up
at vacant site at the junction of GNT Road and Inner Ring Road, measuring about
eight acres near the 100-acre truck yard, is being done hurriedly and the
initial planning permission has been rejected.
It is learnt that the bus terminus has no approach road
and plans are on to do away with two public purpose plots allotted for truck
terminal. The public purpose plots should have been converted for bus terminus
usage.
Since the highway can't have direct opening for buses,
the consultants have proposed entry from GNT road to a 40 feet road and then
through a approach road into the bus terminus. But the hitch is that there are
two public purpose plots mainly for truck terminal. This has to be converted
into usage for bus terminus and then demolished.
Sources feel that having a truck and bus terminal side by
side would further complicate the matters causing congestion in the busy
Kolkata Road. It could create traffic snarl and even law and order problem.
Initially, the feasibility report for building the bus
terminus was not favourable due to congestion in Inner Ring Road as a result
the proposal to have bus terminal in Madhavaram was put on hold.
However, a top CMDA official defended the project. He
said that the project has been designed in detail by competent persons. “The
design has been reviewed and required changes are incorporated,” he said.
He also said that government projects can start and take
planning clearance and not planning permission as per the Act.
It is also learnt that CMDA did not have patta besides
the site has a high tension electricity board line which passes through the
site and has to be removed.