Union govt paves the way for North Chennaites to realise Metro dream


Chennai:
Chennai Metro on Wednesday got the much awaited clearance from the Union cabinet for extending the Phase I project to Wimco Nagar.

The project has been awaiting the nod of the Cabinet since Union Urban Development Minister Venkaiah Naidu announced that his ministry has given green light to the project more than a year ago.

The Phase-I extension covers a length of 9.051 km at a total cost of Rs 3770 crore.

This would mean that the first phase project, including the 9km extension would extend the stretch of Chennai Metro to 54km.

The project will be executed by the existing SPV of Government of India and the Government of Tamil Nadu. The project is scheduled to be completed by March 2018.

Out of the project cost, Union government’s share will be Rs 713 crore while that of the state government Rs 916 crore, which include cost of Land and Rehabilitation & Resettlement of Rs 203 crore. The balance amount of Rs. 2,141 crore will be met from loan.


The initial proposal was to have seven
stations in the nine kilometer stretch between Washermenpet to Wimco Nagar in Tiruvotiyur.

These include Korukkupettai, Tondiarpet, Toll Gate, Thangal, Gowri Ashram, Tiruvottiyur and Wimco Nagar. Now plans are on to have two stations in the 2km underground stretch from Washermenpet to Sir Theagaraya College.

A Metro rail source said that since the clearance has been given, the focus would be now on the underground stretch and work would be started anytime now. The tenders has already been called and it is likely that Afcons would undertake the 2.1km underground stretch linking two stations.

While the deadline for the project is March 2018, it is to be seen how soon the process of land acquisition gets over.

Chennai Metro Rail:

Total cost: Rs 14,750 crore

JICA: 59 per cent

TN share: 21 per cent

GOI share: 20 per cent

JICA share: Rs 8646 crore

TN allocates (2015-16 Budget): Rs 615.78 cr

Total TN share: Rs 3,105.82 crore (fully paid)

Central share: Rs 2920 crore

Central Pending amount: Rs 1498 crore

Extension of First phase:

Tiruvottriyur to Wimco Nagar: 9 km

Total Cost: Rs 3,770 crore

Funds status: Awaited