Thursday, April 5, 2012

TN’s power woes will come to an end with the linking of southern grid with new grid



C Shivakumar
Chennai:
Tamil Nadu will get only 200 MW of power from Gujarat against the demand 500 MW due to the non-connectivity of southern grid with the new grid and the state's power woes will come to an end once the connectivity is established by 2014, according to a source connected with the project.
"The state has sought 500 MW power to tide over the crisis but currently it will be getting only 200 MW of power through the HVDC link and it will not be able to avail 300 MW of additional power due to lack of connectivity between southern and the new grid which can come into being only on 2014 after laying of 765 KV line between Raichur in Karnataka to Solapur in Maharashtra," according to Power Research and Development Consultants chief general manager K Balaraman.

Speaking to Express on the sidelines of two-day conference on Renewable Energy Sector Policy Challenges here on Wednesday,  Balaraman said "The target to link both southern grid and the new grid, which consists of north, east, west and north-east areas, was expected to achieved by December 2013. Now the issue of inter-connectivity will be over by 2014," he said.
 He said Gujarat is willing to give power to Tamil Nadu but the hitch is that there is no line available to transmit the full 500 MW power to the state. “Once this link is established, not only Gujarat, which is a power surplus state, but other northern states will be able to export power to the state,” he added.
He said the linking of the grid would ensure seamless transfer of power from southern region and the rest of the country. He also said the best way is to purchase power from energy source rather than going in for import of coal which is too costly.

Balaraman also denied allegations that the transmission and distribution loss from Koodankulam nuclear plant will be more. He said the transmission and distribution would be least and not more than two per cent as it can be evacuated by the 400 KV system.