Chennai:
Chief Minister J Jayalalithaa will inaugurate the 100 MLD
desalination plant once the work is completed, according to Municipal
Administration and Rural Development Minister K P Munnusamy.
Speaking after reviewing works at the desalination plant
here on Monday, the minister said that laying of 64.37 km pipeline has been
completed. He also said the pumping station at Nemelli, Akarai, Tiruvanmiyur
and Velachery with a combined capacity of 1,375 HP has also
been completed.
Although, he did not give the exact time when the work will
be finished but Metro Water sources said that more than 90 per cent work is
completed except some minor works and the plant is go on stream soon.
The project to be set up with financial assistance from the
Union government, will be the second desalination plant in Chennai. About 265
MLD of raw water from sea will be drawn by gravity by laying 1600 mm pipes for
a length of 1042 metre and after undergoing reverse osmosis, 100 MLD
desalinated water would be produced.