C Shivakumar
Chennai:
The illegal constructions in Chennai
have been thriving due to the connivance of few corrupt Chennai Metropolitan
Development Authority officials who allegedly have links to real estate
agencies in different guises.
Some of the officials, including
some currently serving in enforcement wing and area plans unit, have links to
real estate firms, which is in their wives or relatives name and playing the
role of brokers to move the files.
Surprisingly, this also comes in the
wake of Madras High Court coming out strongly against the CMDA officials for
failure to enforce the planning laws.
Thirty one officers of the CMDA, who
are responsible for failure to enforce the planning laws and thereby paved the
way for unauthorised constructions were impleaded by the High Court.
The lack of action and the failure
to fix the responsibility has emboldened many of the officials. Even, Directorate of Vigilance and Anti-Corruption suggestion to initiate disciplinary proceedings against
these officials failed as CMDA dropped charges against corrupt officials.
Some of the cases which
resulted in DVAC probe included Manapakam unauthorized construction, T Nagar
unauthorized construction, Anna Nagar unauthorized construction, cases
pertaining to Hotel Shan, a fake non-objection certificate resulting in
awarding of completion certificate and cases relating to Choolaimedu
unauthorized construction.
Sources said in all the cases
DVAC conducted a detailed enquiry and submitted the report to the government
which issues a Government Order for disciplinary proceedings against erring
officials by CMDA.
Interestingly, none of the
officials are punished so far. Sources say the lack of action against those
tainted officials is that most of the enquiry is dropped due to procedural
lapses which include lack of manpower, availability of vehicles as well as huge
work load besides various other petty reasons.
“Till now hardly any punitive action
has been taken against the CMDA employees and even the top officials are aware
of the time taken to clear the file,” a builder, on condition of anonymity
said.
But the biggest culprit is the legal
cell of CMDA. “They never vacate the stay in the court,” says a builder who has
been fighting a legal battle over a property.
“If one goes by the number of lock
and seal cases pending in the court and the failure to vacate the stay by the
legal department. Then one can get a clearer picture on the ground reality,” he
says.
Deivasahayam says the officials in
CMDA allegedly try to use the opportunity as there is no system to monitor the
buildings. “If a stop work notice is issued, then it is time for them to make
money,” he alleges.