MRTS second Phase extension deadline revised to March 2018

Chennai:
 The deadline for Phase II extension of Mass Rapid Transit System (MRTS) from Velachey to St Thomas Mount. has been extended to March 2018 as per revised plan.

The deadline has been revised as the project has been hit over payment of compensation to land owners under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The earlier deadline was December 2016.

It is learnt that the state government issued Government Order on February 11, 2011 to acquire land under land acquisition Act 1894 for the formation of railway line between Velachery to St Thomas Mount under the Phase II extension project. 

The land price then was fixed at Rs 2272 per square feet and was sent to commissioner of land administration and the interim award was announced only on September 2014, when the new land acquisition Act came into being. 

This resulted in section of land owners approaching court which asked the government to follow Section 40 (3) of the Right to Fair Compensation and Transparency in the land acquisition Rehabilitation and Resettlement Act 2013 and tender interim compensation to respective property owners.

Following the order, the government agreed to pay 80pc of interim compensation to land owners on December 2015 by adding the land value estimated by the land acquisition officer for passing interim award along with 100pc solution compensation towards structure and trees. 

As a result, the total compensation for acquisition of the land from Velachery to St Thomas Mount is worked out at Rs 8.62 crore. Sources said the consolidated value per square feet as per new award works out to Rs 4629 per square feet to Rs 5,094 per square feet which is higher than the earlier award being fixed.

The delay in passing the award is attributed to administrative reasons.


The proposed alignment and extension of Phase-II took place in the year 2008 and till now 3.7 km out of the 5 km stretch of MRTS line has been completed.



Factfile:
MRTS Phase II Extension
Total stretch: 5km
Target: March 2018
Work completed: 3.7km
Total Cost: 495.74 crore
Union govt share: 165.24 crore
TN share: 330.5 crore
TN already spent: Rs 330.50 crore
Cumulative expenditure (Oct 2016): Rs 369.26 crore