Chennai:
Initial
Operational Clearance (IOC-1) for Light Combat Aircraft (LCA), Tejas has
already been obtained in January 2011. Defence Research and Development Organisation
(DRDO), Aeronautical Development Agency (ADA) and Hindustan Aeronautics Limited
(HAL) are working towards meeting planned schedules for IOC-2 by end of 2013
and Final Operational Clearance (FOC) by end of 2014 to make Tejas fully combat
worthy.
Project
Definition Phase (PDP) for development of LCA was sanctioned in August 1983 at
a cost of Rs 560 Cr. After completion of PDP, Full Scale Engineering
Development (FSED) Programme Phase-I was sanctioned in April 1993 at a cost of
Rs. 2188 Cr (including PDP cost Rs 560 Cr) with increased scope.
FSED
Programme Phase-I was successfully completed in March 2004 and technology was
demonstrated. FSED Programme Phase-II was sanctioned in November 2001 at a cost
of Rs. 3301.78 Cr to build 3 prototypes, 8 Limited Series Production (LSP)
aircraft and establish infrastructure for producing 8 aircraft per year.
Additional
sanction of Rs. 2475.78 Cr was given to meet the financial requirements of FSED
Programme Phase-II for induction into Indian Air Force by obtaining IOC and
FOC. The total sanctioned cost for development of LCA, Tejas (PDP + FSED
Phase-I + FSED Phase-II) is Rs. 7965.56 Cr.